About 45 km southeast of Jakarta, starting in 1992, Cikarang
Listrindo began the building of its first power plant in the heart of
Jababeka Industrial Estate and since then has set the pace for
industrial development by providing its customers with a high quality
supply of electricity. More than 2,350 customers in 5 industrial estates
trust Cikarang Listrindo to deliver reliable and stable power.
Among those customers are national and international/multinational
manufacturers in such sectors as automobiles, electronics, plastics,
food and chemicals. They include blue-chip corporations such as PT Astra
Honda Motor, PT Mattel Indonesia, PT Omron Manufacturing of Indonesia,
PT Komatsu Undercarriage Indonesia, PT Mayora Indah, PT Aisin Indonesia,
PT Yanmar Indonesia, PT AJE Indonesia, PT Mitsubishi Electric
Automotive, PT Enkei Indonesia, PT Jotun Indonesia, PT Kao Indonesia, PT
Kansai Paint Indonesia, PT Kayaba Indonesia and PT Showa Indonesia
Manufacturing along with many leading national companies.
To meet the industrial customers’ growing demand and to have a more
reliable electricity supply system, Cikarang Listrindo continually
invests to increase the plant capacity such as in 2015, when Cikarang
Listrindo started operation of its additional power plant capacity of
109 MW in Megalopolis Manunggal 2100 Industrial Town. With the further
addition of a 2×140 MW Coal-Fired Power Plant at Babelan in 2017,
Cikarang Listrindo reached a combined plant capacity of 1,144 MW. An
expansion program to raise available power up to 1,144 MW is in
progress. Besides satisfying the demand of its industrial customers the
company exports power to the national electricity grid of PLN. The
company is committed to providing all its customers with the highest
level of service in meeting their needs for stable and reliable power.
Seamless and smooth supply of electricity gives customers a significant
advantage in their operations and affords a level of reliability
unsurpassed in Indonesia’s energy market.
Cikarang Listrindo is well known for giving complete and continuing customer satisfaction. Cikarang Listrindo POWR
Vision
Our Vision is to become a world-class power producer.
Mission
Our Mission is to excel in the electricity supply industry with good
teamwork to meet our Customers’ needs for safe, reliable, clean and
efficient power in a friendly and professional manner.
Corporate Values
The Company’s employees uphold integrity in performing their duties and believe in the following values :
Service
- Helping others
- Caring
- Sincerity
Trustworthiness
- Mutual respect
- Engagement
- Synergy
- Honesty
Accountability
- Commitment
- Totality
- Walk the talk
- Responsibility
1992
One of the first steps in the development of our first plant was to
build the 150 kV switchyard which interconnects the power plant with the
national electricity grid, the Java-Bali system.
1993
The first two GE Frame 6 gas turbines were installed in 1993 and provided a plant capacity of 60 MW.
1996
In 1996 the company added another four GE Frame 6 gas turbines and increased the capacity to 180MW.
1998
In 1998 Cikarang Listrindo added two Mitsubishi steam turbines, each
capable of delivering 60 MW. By building two combined-cycle blocks, each
consisting of three gas turbines, three heat recovery steam generators
and one steam turbine, the total capacity reached 300 MW.
2000
In 2000 Cikarang Listrindo was awarded ISO 9001 Quality Management System certification.
2006
In 2006 a GE Frame 9 gas turbine was added, delivering 109 MW and increasing the plant total capacity to 409 MW.
2009
After adding another GE Frame 9 gas turbine in 2009, Cikarang Listrindo
was able to produce a total capacity of 518 MW: another milestone in
utilizing superior technology and providing customers with world-class
quality power supply.
2011
In 2011 Cikarang Listrindo added two Alstom heat recovery steam
generators and one Siemens 128 MW steam turbine to operate in
combined-cycle mode with the two GE Frame 9 gas turbines and bring the
plant capacity to 646 MW.
2012
12 the addition of a third GE Frame 9 gas turbine increased the available power to 755 MW.
2014
In 2014 Cikarang Listrindo was awarded ISO 14001 Environment Management
System and OHSAS 18001 Health and Safety Management System
certification.
2015
In 2015 a second power plant, which is located in Megalopolis Manunggal
2100 Industrial Town, delivered a plant capacity of 109 MW. This raised
the total capacity of the two interconnected plants to 864 MW.
2016
In 2016 Cikarang Listrindo completed a US$272 million IPO on the IDX.
Moreover, the Company achieved a record-breaking high of 1 million KVA
contracted capacity in the same year.
2017
In
2017 the coal-fired power plant in Babelan was installed with two
Valmet (circulating fluidized bed) boilers and two Siemens steam
turbines delivering a plant capacity of 280 MW, and increasing the total
capacity of the three interconnected plants to 1,144 MW. The coal-fired
power plant in Babelan is connected to the 150kV transmission line of
over 30km. Cikarang Listrindo POWR
Cikarang Listrindo is committed to the ongoing implementation of good corporate governance (GCG). The Company’s Code of Good Corporate Governance is intended as a foundation and guideline in managing the Company.
The principles of GCG are implemented pursuant to the Law No. 40 of 2007 on Limited Liability Corporations, Law No. 8 of 1995 on Capital Markets, the Company’s Articles of Association, regulations of the Indonesian Financial Services Authority (OJK – Otoritas Jasa Keuangan, previously known as Bapepam and LK), regulations of the Indonesia Stock Exchange (IDX), other prevailing laws and regulations and GCG principles covering transparency, accountability, responsibility, independence and fairness.
Cikarang Listrindo has published documents supporting the implementation of GCG such as a Code of Good Corporate Governance, a Board Manual and a Code of Conduct.
Audit Committee
The Audit Committee is established under a resolution of the Board of Commissioners of the Company to assist the Board professionally and independently to encourage the formation of an adequate internal supervisory body, improve transparency in financial reporting, review the scope of work and the appointment of the external auditor including but not limited to the fairness of the audit fee, experience, independence and objectivity, and implementation of the risk management and compliance level with the prevailing law and regulations.
Nomination and Remuneration Committee
The Nomination and Remuneration Committee is established under a resolution of the Board of Commissioners of the Company to carry out the functions and duties of the Board of Commissioners in relation to the nomination and remuneration of the Board of Directors and the Board of Commissioners. Cikarang Listrindo POWR
Cikarang Listrindo is committed to the ongoing implementation of good corporate governance (GCG). The Company’s Code of Good Corporate Governance is intended as a foundation and guideline in managing the Company.
The principles of GCG are implemented pursuant to the Law No. 40 of 2007 on Limited Liability Corporations, Law No. 8 of 1995 on Capital Markets, the Company’s Articles of Association, regulations of the Indonesian Financial Services Authority (OJK – Otoritas Jasa Keuangan, previously known as Bapepam and LK), regulations of the Indonesia Stock Exchange (IDX), other prevailing laws and regulations and GCG principles covering transparency, accountability, responsibility, independence and fairness.
Cikarang Listrindo has published documents supporting the implementation of GCG such as a Code of Good Corporate Governance, a Board Manual and a Code of Conduct.
COMMITTEES
In performing its oversight duties, the Board of Commissioners is assisted by the following two Committees:Audit Committee
The Audit Committee is established under a resolution of the Board of Commissioners of the Company to assist the Board professionally and independently to encourage the formation of an adequate internal supervisory body, improve transparency in financial reporting, review the scope of work and the appointment of the external auditor including but not limited to the fairness of the audit fee, experience, independence and objectivity, and implementation of the risk management and compliance level with the prevailing law and regulations.
Nomination and Remuneration Committee
The Nomination and Remuneration Committee is established under a resolution of the Board of Commissioners of the Company to carry out the functions and duties of the Board of Commissioners in relation to the nomination and remuneration of the Board of Directors and the Board of Commissioners. Cikarang Listrindo POWR
Quality
24 Hours
A customer hotline is open 24 hours a day manned by experienced members of staff who attend to all customers’ needs.Security
The well-trained security team of Cikarang Listrindo takes care of all aspects in securing each plant and its transmission and distribution equipment. This is not restricted to the plant itself but includes outer areas in the neighborhood and involves the checking of sensitive facilities such as substations and other power installations.Substation Maintenance
Every medium voltage customer has its own 20 kV substation. Cikarang Listrindo’s experienced service teams take care of monitoring and regular maintenance. Staff regularly attend seminars and training. The company’s service teams are always up to date with latest developments in testing, monitoring and analyzing technology of distribution systems and therefore are able to give a swift and professional response at all times.Fire Trucks
In the power supply industry it is imperative to have a first class safety system. Safety is a key priority in all operations of Cikarang Listrindo. This includes a highly trained fire brigade. Being always prepared for any adverse circumstances is crucial. Cikarang Listrindo has its own fire trucks, which can also help out in cases of emergency in the surrounding area and the brigade carries out fire drills regularly.Calibration of kWh Meters
In order to best serve its customers and to ensure precise billing statements Cikarang Listrindo has its own energy meter calibration department where all meters are carefully inspected and calibrated on a regular basis. Cikarang Listrindo POWRInfrastructure
Main Control Room
The heart of the power plant is the main control room. All operations of the plant are continuously monitored. By utilizing state-of-the art equipment the engineers of Cikarang Listrindo ensure stable operation.Distribution Control Centre/SCADA Room
In order to ensure that all customers receive steady power supply, the distribution of electricity is also continuously monitored from a Distribution Control Centre / SCADA Room. This is another key factor in the reliability of Cikarang Listrindo.20kV Distribution Boards
After being stepped down from 150 to 20 kV the electricity supply is distributed to Cikarang Listrindo’s customers in all five industrial estates. Flawless performance is crucial and the status of distribution boards and systems is closely observed.Additionally Cikarang Listrindo’s medium voltage customers have the privileged advantage of two incoming feeder lines: a normal and a stand-by supply line. This feature provides continuous power supply for its customers 24 hours a day 7 days a week.
Chemist Laboratory
Cikarang Listrindo makes its environmental responsibility one of its top priorities. Chemical engineers routinely analyze the quality of the cooling water. Clean water is imperative for smooth steam turbine operation and an important point in the company’s commitment to deliver clean energy both to serve its customers and maintain the environment.Gas Compressors
Efficient performance of the gas-fired plants depends on steady gas supply and stable gas pressure for proper operation of the gas turbines. Cikarang Listrindo has installed three dedicated gas compressors in Jababeka Plant and another two in MM2100 Plant, to deliver the correct gas pressure to the gas turbines at all times. Cikarang Listrindo POWREnvironment
Cikarang Listrindo views Health, Safety and Environment (HSE) as
critical to all its employees and customers in all operations and the
company is committed to continually improve its performance. The HSE
policies are overseen by a board of directors which provides direction
for the management of HSE and input on current and emerging health,
safety and environmental issues such as:
- HSE Training
- Safe Working Practices
- Drugs and Alcohol Policy
- Smoking in the Workplace Policy
Cikarang Listrindo was recognized for its commitment to employee
health and safety and was awarded OHSAS 18001 Occupational Health and
Safety Management Systems certification in 2014. Cikarang Listrindo POWR
Head Office:
World Trade Centre 1, 17th Floor
Jl. Jend. Sudirman Kav. 29-31
Jakarta 12920, Indonesia
Jakarta 12920, Indonesia
Telphone (021) 5228122, 2522145
Facsimile (021) 5224440